How Long Does a Wet Room Take? A Day-by-Day Programme

Wet rooms take longer than a standard shower refit for one simple reason: waterproofing needs time to cure properly before anything is built on top of it, and that time can't sensibly be rushed. This guide walks through a realistic day-by-day programme for a typical wet room installation, and the things that most commonly push a job beyond its planned schedule.

Key takeaways

  • A typical wet room runs 8-10 working days, a simple en-suite can be quicker.
  • Curing and flood-test time for screed and membrane genuinely cannot be safely compressed.
  • Unexpected floor structure issues are the leading cause of overruns, hence the value of a proper survey first.
  • A written stage-by-stage schedule agreed before work starts gives you a clear benchmark.

Day 1-2: strip out and first fix

The first stage is stripping the existing bathroom back to the structure, removing old sanitaryware, tiling and, where needed, floor boarding to expose the joists or slab beneath. First-fix plumbing and electrics happen alongside this, running new pipework for the shower valve and any additional outlets, and cabling for lighting, extraction and underfloor heating if specified.

On a suspended timber floor this stage also includes any structural preparation identified at survey, addressing deflection, or adjusting joists ahead of the deck former going in, which can add a day if the floor needs more than routine work.

Day 2-3: floor preparation and deck former or screed

With first fix complete, the floor build-up goes in, either a deck former system on timber joists or a screed fall on a concrete slab, along with the drain body itself. This stage needs to be done accurately, since it determines the fall the whole room will have permanently, and it needs to be fully set or cured before waterproofing can begin.

This is one of the stages that genuinely can't be rushed. A screed, in particular, needs adequate time to cure before membrane goes over it, and pushing ahead too early is one of the more common causes of later problems.

Day 3-5: tanking, curing and flood testing

Waterproofing membrane goes onto the floor and walls in this stage, with reinforcing tape at all corners, joints and penetrations. Depending on the product, this typically needs at least 24 hours between coats and further time to cure fully before a flood test can be carried out safely.

A flood test, filling the floor to a shallow depth and leaving it for around 24 hours to check for any drop in level, adds a further day but is one of the most valuable checkpoints in the whole build, catching any issue with the membrane or drain seal before tiling covers it up.

Day 5-8: tiling

Once the flood test has passed, tiling begins, generally starting with the walls before the floor, or in some sequences the floor first depending on the fitter's method and the drain type. Large-format tiles take longer to lay accurately, particularly around a linear drain fall, and any bespoke cutting around fittings, niches or a glass screen fixing adds time here too.

Grout then needs its own curing time before the room can be used, typically at least 24 hours, sometimes longer for wider grout joints or certain grout types, so this isn't a stage to compress even when the rest of the project is running to schedule.

Day 8-10: second fix and finishing

The final stage covers fitting the shower screen if specified, second-fix plumbing to connect the shower valve and any basin or WC, second-fix electrics for lighting, extraction fan and any heated elements, sealant around junctions, and a final clean. This stage also includes commissioning any underfloor heating and testing extraction is working correctly.

A full wet room, including a WC and basin alongside the shower area, will sit towards the higher end of this range, while a simple en-suite shower-only conversion can come in closer to a week overall.

What causes overruns and how to avoid them

The most common cause of delay is discovering an unexpected floor or structural issue once boards are lifted, rot, inadequate joist depth or an awkward existing waste run, which is exactly why a thorough survey before quoting matters so much. The second most common cause is rushing curing times for screed, membrane or grout to hit a deadline, which risks the very problems tanking is meant to prevent.

Supply delays on a specific tile, drain or fitting can also add time if a bespoke item is chosen, so ordering materials as early as possible in the process, ideally confirmed at the design and quote stage, helps keep the programme on track. A written schedule setting out each stage, agreed before work starts, gives you a clear benchmark to check progress against as the job proceeds.

Quick questions

Can a wet room be finished faster than 8-10 days?

A very straightforward en-suite conversion on a solid floor with no structural issues can sometimes complete in around a week, but curing times for screed, membrane and grout set a practical floor beneath which it's not sensible to compress the schedule.

Can I use the wet room before the grout has fully cured?

It's best avoided. Using the shower before grout has properly cured risks trapping moisture and weakening the joint over time, even though it may look and feel dry to the touch within a day or so.

Does a linear drain take longer to install than a point drain?

Slightly, generally, because the fall needs to be consistent over a longer run and the drain channel itself often needs precise levelling, but the difference is usually measured in hours rather than days on a typical project.

Why do quotes vary so much on timescale for what looks like the same job?

Floor structure is the biggest hidden variable, a solid floor with straightforward access can be quicker than a suspended timber floor needing structural preparation, even if the finished wet room looks identical once tiled.

What happens if the flood test fails?

The membrane or drain seal is investigated and repaired before tiling proceeds, which understandably adds time to the programme, but it is far preferable to finding the same fault after the room has been tiled and is in daily use.