Downstairs cloakroom installations in tight spaces

The short answer

A cloakroom is the cheapest square metre of value in most houses, and the one most often botched. Under the stairs, in a hall recess or off a utility, the constraint is headroom and waste.

What decides the layout

Under stairs, position the WC where headroom
exceeds around 1.9m at the front of the pan; a short-projection pan and a rear-outlet trap buy the extra room.
Where the soil stack is on the far side of the house
a small-bore pumped waste is a reasonable answer providing the run is planned with access for servicing.
A compact 400mm basin with a bottle trap
and a wall-hung tap frees the floor and makes the room mopable.

Questions we get asked

Does a cloakroom need a window?

No, but it needs extraction with an overrun, ducted to outside. An internal cloakroom without ventilation will get damp and smell.

How long does a cloakroom take?

Typically several working days once drainage, first fix, boarding, tiling and second fix are sequenced properly, longer if a new waste run is being formed.

compact family bathroom refit #1, Newent, Cotswold Maintenance Group portfolio, referenced in our guide to downstairs cloakrooms

Ready to get the room measured up?

Photos of the existing room and the position of the soil stack help enormously before a visit.